Jimmy Chavis can personally oversee the installation of your modular
home. How do we do it?
Laying Out The Site and Building the Foundation
Install temporary power and have electricity hooked up. Lay out site,
install batter boards, dig foundation trenches and install the
foundation forms. Pour footings, build foundation walls and piers, and
install mud sills. Have the foundation inspected.
Setting House Units
Work crews lift components by crane onto the foundation.
Roofing
Install knee boards, collar ties and rafter supports. Install gable end
walls, structure wood and supports. Install roof vents. Install roof
underlayment and shingles on hinge rows. Install ridge cap shingles.
Dormers
If applicable, cut out roof, install dormer walls, trusses, roof
decking, roof edge, tar paper, roll roofing in valleys, install
shingles, metal flashing on front wall, install windows and finish trim.
Exterior
Complete installation of exterior siding and trim, soffit and fascia.
install windows in gable ends. Paint exterior doors and door jambs.
Install shutters and optional exterior storm/security doors. Install
landscaping.
Complete Plumbing, Wiring and Utility Hookups
Install any under floor mechanicals, under floor plumbing and electrical
work. Complete electrical hookup throughout home. inspect pipelines
below or through the foundation. Provide plumbing connections for water
and heater throughout home. Install exterior water faucets. Cut dryer
vents through floor and the exterior of the house. Inspection of
plumbing and wiring. Provide electrical service from power company. Have
electric, gas and water utilities turned on.
Heating and Cooling
Install heating and air conditioning systems. Inspection of heating and
air conditioning systems.
Steps, Porches, Decks, Driveways and Sidewalks
Install steps, porches, decks, driveways and sidewalks where applicable.
Interior
Finish interior wall and ceiling drywall repairs and painting. Complete
installation of archway and casing. Install stairway walls, drywall, and
stair rails to second floor and paint, where applicable. Finish
flooring, carpet to carpet splice, carpet to tile splice. Finish
installing interior doors and trim. Finish installing light fixures and
ceiling fans. Finish installing shower doors, appliances and
accessories.
Completion
Clean up site outside and clean inside. Provide grading and seeding of
disturbed land areas. Have the final inspection and secure certificate
of occupancy. Move in.
|




 |
|